# Demurrage and Laytime

> Laytime is the time a charter allows to load or discharge a vessel. Demurrage is the agreed daily rate the charterer pays the owner once laytime runs out.

- Publisher: Navarik
- Web page: https://www.navarik.com/resources/glossary/demurrage-and-laytime/
- Related solution: [Demurrage & Laytime](https://www.navarik.com/solutions/demurrage-laytime/)
- Related solution: [Operations & Scheduling](https://www.navarik.com/solutions/operations-scheduling/)

Laytime is the time a voyage charter allows for loading and discharging a vessel without extra payment. Demurrage is
the compensation the charterer pays the shipowner, at an agreed daily rate, for every hour the vessel is held beyond
that allowance. Both are set in the charter party, and the cost usually flows on to whoever caused the delay: the
terminal, the refinery, the supplier or the buyer.

## How laytime is counted

- **Allowance.** Tanker charters often allow a fixed number of hours in total for loading and discharging. Dry bulk
  charters more often express laytime as a rate, such as tonnes per day.
- **Start.** The master tenders a notice of readiness (NOR) when the vessel has arrived and is ready to load or
  discharge. Laytime usually starts after a notice period, or when the vessel is all fast at the berth if that is
  sooner, depending on the charter's terms.
- **Exceptions.** Some time doesn't count, or counts at half rate: for example shifting from anchorage to the berth,
  delays caused by the vessel itself, or periods excluded by the charter. Delays at the terminal generally count
  against the charterer.
- **End.** Laytime normally stops when hoses are disconnected and documents are on board.

The times come from the statement of facts (SOF), the agreed record of the vessel's arrival, berthing, pumping and
departure, which is the basis of the laytime calculation.

## How demurrage is calculated

Once laytime is used up, the vessel is on demurrage. Demurrage is charged per day, pro rata for part days, at the rate
in the charter party. Under many charters, once a vessel is on demurrage the exceptions that would have stopped
laytime no longer apply. Some charters also pay despatch, a reward for finishing early, though this is less common for
tankers.

## Example

| | Hours |
|---|---|
| Laytime allowed for loading and discharging | 72 |
| Time used, from the statement of facts | 102 |
| Time on demurrage | 30 |

At a demurrage rate of $45,000 a day, 30 hours costs 30 ÷ 24 × $45,000 = **$56,250**.

## Why it matters

Demurrage is often treated as a cost of doing business, but each claim points to a cause: berth congestion, tank
space, slow pumping, late documents or a quality hold. Claims also have time bars. Many tanker charters require the
claim and its supporting documents within a set period, commonly around 90 days, after which it can be lost. Records
of NOR, berthing and pumping times are what win or defend a claim.

## How Navarik helps

OAS schedules berths and forecasts demurrage exposure before vessels arrive, so refineries and terminals can see which
arrivals will run over laytime. NI records laytime events, NOR and demurrage documentation against each nomination.
See [Demurrage & Laytime](https://www.navarik.com/solutions/demurrage-laytime/), and our guide to
[the three types of refinery demurrage](https://www.navarik.com/resources/guides/refinery-demurrage-right-problem/).